domingo, 25 de novembro de 2012

Construction update: Nov 25, 2012

Second phase almost complete! On the pictures below, it is possible to see that the walls are all ready, and so are the plumbing (water and sewer), the frames, including some windows that have been fixed (the others were achieved), and the structure for the roof has been prepared for receiving the wood beams. It is also possible to see that a great part of the material has been achieved, including for the third phase. The last picture shows the sign saying that the school is open for registration for 2013, including the 4rth grade! This will only be possible because the new room will be ready for the kids next year!

sexta-feira, 16 de novembro de 2012

First pictures and follow up

This week, we started the first phase. Check the pictures of the building site and the timeline.



Project PhaseDate Money available in BrazilFromToDuration (Days)ActivitiesCost Involved (Brazilian Real)Cost Involved(Euro, Real/Euro conversion rate from date 16/11/2012)
I4121401/11/1216/11/1216Purchase and storage of material, preparation of the site and started the foundationsR$ 6.190,00€2.392,67
II16/11/201216/12/201230Foundation, structure, masonry (walls)
Electrical wiring, plumbing (water and sewer), frames (windows and openings) and coverage (structure and roof, lined)
R$ 3.500,00€1.500,00
III16/12/201215/01/201330Plastering, painting, flooring, finishes, doors, baseboards, light fixtures, outlets and switches, installation of sanitary wares and metals. Clean the workR$ 2.810,00€1.107,33
R$ 12.500,00€5.000,00
Project Kick-off date01/11/2012

segunda-feira, 5 de novembro de 2012

Starting to buy building stuff

The money has finally reached the project's account, and we started to buy the material. Soon we will be publishing the receipts.

domingo, 21 de outubro de 2012

Preparing to start up

This week we received great news: our sponsor informs that the money for the first phase was credited to the project's account. While we wait for the money to arrive, we are comparing prices for the material to be used in the construction.

domingo, 15 de julho de 2012

Project He Space Children's Foundation Brazil 2012 will finance the construction of a school classroom at Estação Vida, a school held by an NGO that provides education for children in need. Above 80% of the students live in a neighbour nursing home, in the city of Águas Lindas de Goiás, in the center region of Brazil. This home houses children who are taken from their families by the Justice, due to danger exposure (violence, abuse, abandon, etc). The home is exclusively supported by donators, as it does not receive any kind of government support.

We created this weblog so that our European friends can keep in touch with the project stage.